Case study · Large Integrated Energy Company

Improved Well Planning Process

Adoption of a common repeatable well planning process delivering alignment between client and JV partner

The challenge

Insufficient front-end loading during well planning, resulting in late changes to design

Misalignment with JV partner on targets causing rework late in the planning process and subsequent delays

Sub-optimal well planning processes for $1.5BN deepwater wells project

Successful outcome

  • Adoption of a common repeatable well planning process delivering alignment between client and JV partner
  • Reduced planning time and engineering hours by eliminating late changes and rework
  • Increased operational flexibility by having wells -ready-to-go
  • Reduced rework by >60% delivering significant savings per well
  • Greatly improved rig schedule to facilitate more accurate well delivery plans

How we did it

  • Designed and implemented a common process, including templates, specific to deepwater wells to streamline planning, increase collaboration, and reduce rework
  • Introduced decision tools to facilitate agreement and shared objectives between client and JV partners
  • Tightly integrated engineering technical practices into planning process to facilitate earlier alignment with review and approval stage gates

Boxley Group competencies

  • Oil and Gas Domain Knowledge - Well Planning
  • Process Optimization
  • Project Management